Waller Hall

DATE:
April 27, 2012
CURRENT ACTIVITY:
PHASE 4-1 & 4-2:
- Scott and From—Duct Installation
- Aries Mechanical—AC plumbing in
mezzanine mechanical room
- Sound Energy—DDC control
installation
- Danard Electric—VAV electrical
PHASE 7 MECHANICAL ROOM:
- Sound Energy—DDC control
installation
- Danard Electric—VAV Electric
- Aries Mechanical— Chilled water
pump installation and boiler
circulation pump reconfiguration
UPCOMING ACTIVITIES:
MILESTONES:
- May 3, 2012—Phase 4 Completion
- May 7, 2012—Begin Phase 4 TAB