Waller Hall

DATE:

April 27, 2012

 

CURRENT ACTIVITY:

PHASE 4-1 & 4-2:

  • Scott and From—Duct Installation
  • Aries Mechanical—AC plumbing in mezzanine mechanical room
  • Sound Energy—DDC control installation
  • Danard Electric—VAV electrical


PHASE 7 MECHANICAL ROOM
:

  • Sound Energy—DDC control installation
  • Danard Electric—VAV Electric
  • Aries Mechanical— Chilled water pump installation and boiler circulation pump reconfiguration

UPCOMING ACTIVITIES:

MILESTONES:

  • May 3, 2012—Phase 4 Completion
  • May 7, 2012—Begin Phase 4 TAB

 