WPC
< BACK TO CURRENT PROJECTS

 

CURRENT PROJECTS

St Paul Modular Buildings

DATE:

February 21, 2011

 

CURRENT ACTIVITY:

  • This week the TGSPI crew completed exterior wall 
    framing of Units 2 &3.  Exterior wall framing is now 
    complete on all three units.  The WPC crew 
    completed setting all the trusses on Unit 1 Monday 
    and has moved onto framing the parapet and rooftop 
    pony walls for Unit 2.  They plan on setting Unit 2 
    trusses over the weekend, and then moving onto 
    Unit 3.  The TGSPI crew started installation of blocking 
    and sheathing the exterior walls on Unit 1 Thursday.  
    They will continue through next week.    BOE 
    architects pllc and AHBL Engineers have been working 
    on revisions to the final floor plans and details, and will 
    have final plans ready Tuesday of next week. 

 

UPCOMING ACTIVITY:

  • Truss Installation ‐ Unit 2 
  • Exterior Wall Sheathing ‐ All Units
  • Roof Parapet Wall Framing ‐ Unit 3 
  • Truss Installation - Unit 3

 

MILESTONES:

  • 3/31— Unit 2 Trusses Complete 
  • 3/4— Unit 3 Truss Installation Start 
  • 3/7—Roof Sheathing Start 

 

< PREVIOUS UPDATE

 


DRAWINGS

More Info - Files may be large - Right Click to Download

© 2010 WPC / PO Box 1728 / 10421 Burnham Dr NW, Gig Harbor, WA 98335 Contact Us / Help