St Paul Modular Buildings

DATE:
February 21, 2011
CURRENT ACTIVITY:
- This week the TGSPI crew completed exterior wall
framing of Units 2 &3. Exterior wall framing is now
complete on all three units. The WPC crew
completed setting all the trusses on Unit 1 Monday
and has moved onto framing the parapet and rooftop
pony walls for Unit 2. They plan on setting Unit 2
trusses over the weekend, and then moving onto
Unit 3. The TGSPI crew started installation of blocking
and sheathing the exterior walls on Unit 1 Thursday.
They will continue through next week. BOE
architects pllc and AHBL Engineers have been working
on revisions to the final floor plans and details, and will
have final plans ready Tuesday of next week.
UPCOMING ACTIVITY:
- Truss Installation ‐ Unit 2
- Exterior Wall Sheathing ‐ All Units
- Roof Parapet Wall Framing ‐ Unit 3
- Truss Installation - Unit 3
MILESTONES:
- 3/31— Unit 2 Trusses Complete
- 3/4— Unit 3 Truss Installation Start
- 3/7—Roof Sheathing Start
|